A bathroom is a small room with a lot going on: plumbing, electrics, waterproofing, tiling and decorating, in a strict order. This is how the weeks usually run.
Before we start
We survey the room, check pipes and walls, and agree the layout. You choose tiles and sanitaryware, and everything is ordered so it is on site when needed. You receive a fixed written price and a day-by-day plan.
Week 1: strip-out and first fix
- The old bathroom is removed and taken away.
- Pipework and cables are moved to suit the new layout.
- Walls and floor are repaired and prepared.
- Wet areas are waterproofed (tanked) before any tile goes on.
This is the noisy, dusty week. It is also when the water is off for the longest, and your plan shows exactly when.
Week 2: tiling
- Wall and floor tiles are fixed.
- Grouting is completed and left to cure.
Tiling takes longer than people expect, especially with large-format tiles, patterns or niches. Rushing it shows.
Week 3: second fix and finish
- Bath, shower, toilet and basin are fitted.
- Taps, radiator, mirror and lighting go in.
- Painting, silicone sealing and a thorough clean.
- We walk through the finished room with you.
Simpler bathrooms finish within two weeks. Larger rooms, or those with layout changes, need the third.
What can slow it down
- Tiles or fittings that arrive late or damaged
- Hidden problems behind the old tiles, such as damp or rotten joists
- Changes of mind once tiling has started
Choosing everything before the start date avoids most of these.
See your price first
Our bathroom packages start from £11,900. You can see a price for your own room in two minutes on the bathroom calculator, before anyone visits.